After the shelter has been erected, the operator personnel will unbolt selected items of equipment. (See
WP 0002 00, Figure 2). These items will be
relocated to
pre-selected positions on
the expanded side of
the
shelter. (See WP 0002 00, Figure 3). The selected items, when moved, will not be secured (bolted) in place. This
allows the shop personnel certain flexibility in positioning desks and work station tables. The recommended
locations were selected for proper utilization of floor space and maximum safety for the operating personnel.
WARNING
Four people are needed when moving or lifting the ECUs. Each unit weighs
approximately 270 pounds. Trying to move or lift an ECU without sufficient help
can cause SERIOUS INJURY to personnel.
Detailed instructions for unbolting equipment and the recommended sequence for relocating equipment are
contained in WP 0008 00. The procedures for striking the shelter and preparing the Production/Quality Control
Shop for transport or storage are contained in WP 0010 00 through WP 0013 00.
The ECUs are supplied by the unit. Procedures for positioning the ECUs for operation are in WP 0007 00. The
two ECUs are positioned on special fold-down panels when the shop is in the operational mode. Power is
provided by a 208V, 3 phase cable located inside the shelter next to each panel. Both ECUs can be easily
removed for service or repair. Procedures for repositioning the ECUs for transport or storage are in WP 0011 00.
Electrical power to operate the Production/Quality Control Shop is provided by an auxiliary generator or a
commercial power source. A Power Distribution Box (PDB) is used between the power source and the power
entry panel of the shelter. The generator, PDB, and the pigtail used to connect the PDB to the generator are
supplied by the unit. Overload protection is provided by circuit breakers. The circuit breaker panel is located inside
the shelter next to the personnel entrance door. Procedures for connecting electrical power to the shop are in
WP 0006 00. Procedures for disconnecting electrical power from the shop are in
WP 0012 00.