1-90 INSTALLATION IN CONTAINER
(Cont)
11. Check that humidity indicator (17) is blue. Replace
indicator if pink.
12. Wipe mating flanges and gasket of container halves
with clean cloth to remove any dirt or particles, which
could prevent pressure sealing. Lower hoist until
container halves are joined.
13. Lubricate bolts (5) with Lubricating Oil (E.2) or
(E.71) and secure cover to base with bolts (5), washers
(4) and nuts (3). Torque nuts to 270 to 300 inch-pounds,
progressively.