TM55-2840-251-23
SECTION VIII GENERAL MAINTENANCE PROCEDURES (Continued)
1-73
INSTALLATION/REMOVAL OF ENGINE OR
POWER SECTION IN/FROM STANDS
(Cont)
6.
Remove power section from Stand (T. 51) (3) as
follows:
a.
With power section in horizontal position,
install Sling (T. 41) (2) on propeller shaft. Secure with
four capscrews (19). Torque capscrews to 600 to 650
inch-pounds.
b.
Hook up hoist (1) to sling (2) and raise hoist
enough to support the weight of the power section.
c.
Remove 12 nuts (17) and bolts (18)
securing power section to mount ring (6) and move
power section clear of stand (3).
d.
Remove four capscrews and washers (15)
securing mount ring to stand and remove ring.
e.
Remove six nuts (14), washers (13) and
bolts (12) and two adapters (11) from stand.
f.
Refer to Task 4-1-2 Reinstall power section.
1-74
OPERATIONAL CHECK
Refer to Chapter 1, Section X or TM55-1510-209-23.
GO TO NEXT PAGE
1-94