3-2 INNER (SMALL) EXIT DUCT, SHROUD AND VANE ASSEMBLY (AVIM)
(Continued)
3-2-6 INSTALLATION (Cont)
2. If clamp plate is installed,
proceed as follows: (Cont)
NOTE
Observe through holes in
clamp plate that lugs are
engaged and inner support
is correctly seated.
b. Insure there is no
clearance between clamp plate and
outer (large) exit duct.
c. Align offset hole in
clamp plate (3) with similar
hole in compressor bearing cover
flange (4).
NOTE
Later bearing covers have
eight extra holes which
are not used in this
configuration.
d. Secure assembly with
eight silver-plated bolts (1).
Torque bolts to 32 to 36 inch-
pounds and lockwire (E.4) in
pairs.
FOLLOW ON MAINTENANCE:
Installation Compressor Turbine
Assembly (Task 2-3-3)
Installation Liner Assembly
(Task 3-1-4)
END OF TASK