TM 1-4920-438-13&P
0025 00
POWER TRAIN SHOP
25-TON ARBOR PRESS
INITIAL SETUP
Tools And Special Tools:
References:
Tool Kit, Power Plant
MIL-STD-2219
Materials/Parts:
Equipment Conditions:
Functional
Hexagon Head Cap Screw
Personnel Required: (1)
CMF 15 Series
NOTE
During installation of components the same hardware should be used so as to
maintain the original integrity of the shop sets.
INSPECT
Visually inspect 25-Ton Arbor Press mounting bracket for looseness or damage. If a bracket is loose, follow
procedures in WP 0026 00. If a bracket assembly is damaged it must be removed and repaired or replaced.
REMOVE
1. Remove bolts, lock washers, and flat washers attaching bracket to floor.
2. Place hardware in cotton mailing bag.
3. Remove bolts, lock washers, flat washers, and nuts attaching bracket to 25-Ton Arbor Press.
4. Place hardware in cotton mailing bag.
0025 00-5