TM 10-4930-351-14
0109 00
INSTALL DECOMPRESSION LEVER (Refer to Figure 27.)
INITIAL SET-UP:
Tools:
Materials/Parts Required
3 mm key wrench
None
13 mm combination wrench
Equipment Condition:
Fuel injectors installed
1.
Position decompression lever (1) on plates (2), and install and tighten screws (3) and nuts (4).
2.
Operate the decompression lever to ensure freedom of movement.
3
1
4
2
Figure 27. Decompression Lever Installation
0109 00-36