NAVAIR 01-1A-505-3
TO 1-1A-14-3
TM 1-1500-323-24-3
014 02
1 September 2011
Page 50
1. For non-environmental pin contact
0.787"
(620175010 and 620175021) slide alignment
(20 mm)
boot over cable. For environmental pin
contact (620175011 and 620175020) slide
alignment boot equipped with its sealing boot
over cable. Be careful to not damage the
Alignment
sealing boot while sliding it on the cable
Boot
jacket.
2. Strip outer cable jacket to dimensions
shown, IAW NAVAIR 01-1A-505-1 WP 009
Cable Jacket
00
0.630"
16 mm
3. Comb out exposed shield braid and cut the
rod fillers.
4. Trim both center conductors to dimension
shown.
Combed
Center
Conductor
Shield
Cable Jacket
Ferrule
5. Slide ferrule on the cable till butted against
cable jacket.
Ferrule should slide
over cable jacket and
butt at the end of the
jacket.
0.138"
3.5 mm
0.157"
Cable
6. Fold combed shield braid over ferrule and
4.0 mm
trim to dimension.
7. Trim center conductors to correct length
(0.531 inches).
8. Strip center conductors to dimensions
shown, IAW NAVAIR 01-1A-505-1 WP 009
Ferrule
00
0.531"
Shield
13.5 mm
Braid
Center
Conductors
Pin
Center
Center conductor visible in center
Contact
contact inspection hole.
9. Slide center contacts over center
conductors till fully seated. Ensure
Ferrule
conductors are visible in the inspection holes.
10. Crimp center contacts using tools in
Table 6 and NAVAIR 01-1A-505-1, WP 013
00.
Note: While pin and socket contacts are
shown here, the assembly will be supplied
Socket
with and built with 4 pin or 4 socket contacts. Center
Contact
Figure 42. 620175010, 620175021, 620175011 and 620175020 Quadraxial Contact Buildup (Sheet 1 of 2)