10. Slide the intermediate ferrule over the
insulating bushing till fully seated.
Center
Ferrule
Shield
Contact
Insulator
Braid
Bushing
11. Slide the center contact insulator over center contact assembly.
12. Slide the intermediate contact over the sub-assembly.
13. Put the second conductor in the barrel slot of the intermediate contact.
14. Slide the ferrule over the second contact, ensure ferrule does not extend past the intermediate
contact shoulder.
15. Crimp ferrule to intermediate contact using tools in Table 5 and NAVAIR 01-1A-505-1, WP 013 00.
Ensure second conductor is aligned with one of the hexagonal flats before crimping.
Crimp Die
Center
Intermediate
Second
Flat
Cable
Contact
Contact
Conductor
Insulator
Second
Conductor
Ferrule
Contact
Shield
Insulator
Braid
Shoulder
Bushing
16. Slide intermediate contact insulator over intermediate contact.
17. Slide outer contact over intermediate contact insulator till all components are seated.