NAVAIR 01-1A-505-3
TO 1-1A-14-3
TM 1-1500-323-24-3
014 02
1 September 2011
Page 44
Environmental
Boot
1. Slide environmental boot on cable (if
required) prior to stripping.
Cable Jacket
0.709"
18 mm
2. Strip outer cable jacket to dimension shown IAW
NAVAIR 01-1A-505-1 WP 009 00.
Cable Jacket
0.473"
12 mm
3. Comb shield braid and cut high immunity
ribbon. Cut both center conductors to
dimension shown.
Combed
Cable
Ferrule
Shield
Jacket
4. Slide ferrule over shield braid till seated on
cable jacket.
1st
Conductor
Cable
(Blue,
0.217"
0.177"
Jacket
Center
5. Fold shield braid over the cable jacket and
5.5 mm
4.5 mm
Contact)
trim to dimension indicated.
6. Trim center and intermediate conductors to
2nd Conductor
correct length.
(Intermediate
7. Strip center and intermediate conductors to
Contact)
dimensions shown, IAW NAVAIR 01-1A-505-
0.157"
1 WP 009 00
4 mm
Shield Ferrule
0.354"
Braid
9 mm
Center
8. Put the two wires in the insulator until it
Cable
Contact
Jacket
hits the shield braid.
Crimp
9. Slide center wire into center contact.
Area
Ensure dielectric is butted on the shield
braid and that center is visible in contact
inspection hole
10. Crimp center contact using tools in
Center
Table 5 and NAVAIR 01-1A-505-1, WP 013
Contact
00.
Ferrule
Insulator
Bushing
Figure 40. 617150, 617050, 617151 and 617051 Triaxial Contact Buildup (Sheet 1 of 3)